EUD-NET
will balance development of research ideas with industrial feedback and
dissemination of results.
The overall management of the project is the main responsibility of the
Network Coordinator (Dr. Fabio Paterṇ). The coordinator node is
C.N.R., Pisa, Italy.
The Network Management Committee is composed of a representative of each
managing node (Prof. Maria Francesca Costabile – Univ. Bari, Dr.
Nikolay Mehandjiev - UMIST, Prof. Reinhard Oppermann - FIT).
The first EUD-NET workshop
was held on 23 and 24 September.
|
Workpackage list
Deliverables list
|
Workpackage list |
Work-
package N
o
[1]
|
Workpackage title
|
Lead
contractor
N
o
[2]
|
Person-
months
[3]
|
Start
month
[4]
|
End
month
[5]
|
Deliv-
erable
N
o
[6]
|
1 |
Research coordination |
4 |
13,1 |
1 |
12 |
D1.1
D1.2
D1.3
|
2 |
Industrial cooperation |
1 |
10,5 |
1 |
12 |
D2.1
D2.2
D2.3
|
3 |
Information dissemination |
2 |
11,4 |
3 |
12 |
D3.1
D3.2
D3.3
|
4 |
Network Evaluation |
3 |
10 |
3 |
1 |
D4.1 |
5 |
Management and administration |
1 |
11,5 |
1 |
12 |
D5.1
D5.2
D5.3
|
|
TOTAL |
|
56,5 |
|
|
|
[1]
Workpackage number: WP 1 – WP n.
[2]
Number of the contractor leading the work in this workpackage.
[3]
The total number of person-months allocated to each workpackage.
[4]
Relative start date for the work in the specific workpackages, month 0
marking the start of the project, and all other start dates being relative
to this start date.
[5]
Relative end date, month 0 marking the start of the project, and all end
dates being relative to this start date.
[6]
Deliverable number: Number for the deliverable(s)/result(s) mentioned in
the workpackage: D1 - Dn.
Deliverables list
|
Deliv.
No[1]
|
Deliverable title
|
Delivery
date
|
Nature
[2]
|
Dissemination
level
[3]
|
D1.1 |
Roadmap of the field |
6 M/12 M |
R |
PU |
D1.2 |
Identification
of promising research topics for the EC future programme |
6 M/12 M |
R |
PU |
D1.3 |
Two EUD-Net workshop reports |
4M/ 12 M |
R |
PU |
D2.1 |
Action plan for industrial area |
12 M |
R |
PU |
D2.2 |
Industrial forum report |
12 M |
R |
PU |
D3.1 |
Survey
of member research projects, tools, and PhD studies |
12 M |
R |
PU |
D3.2 |
Proceedings
workshop organised in conjunction with a main conference |
12 M |
R |
PU |
D3.3 |
Network web site |
1 M |
O |
PU |
D4.1 |
Evaluation
report; including annotated recommendations for improvements in the
consecutive months |
6 M |
R |
PU |
D5.1 |
Progress
and administrative reports |
6 M / 12M |
R |
PU |
D5.2 |
Minutes
of the executive committee meetings |
1-12 M |
R |
PU |
[1]
Deliverable numbers in order of delivery dates: D1 – Dn
[2]
Please indicate the nature of the deliverable using one of the following
codes:
R = Report
P = Prototype
D = Demonstrator
O = Other
[3]
Please indicate the dissemination level using one of the following codes:
PU = Public.
PP = Restricted to other
programme participants (including the Commission Services).
RE = Restricted to a
group specified by the consortium (including the Commission Services).
CO = Confidential, only
for members of the consortium (including the Commission Services).
|
|
|