EUD-NET will balance development of research ideas with industrial feedback and dissemination of results.

The overall management of the project is the main responsibility of the Network Coordinator (Dr. Fabio Paterṇ). The coordinator node is C.N.R., Pisa, Italy.
The Network Management Committee is composed of a representative of each managing node (Prof. Maria Francesca Costabile – Univ. Bari, Dr. Nikolay Mehandjiev - UMIST, Prof. Reinhard Oppermann - FIT).

The first EUD-NET workshop was held on 23 and 24 September.

Workpackage list
Deliverables list

 

Workpackage list
Work-
package
N o [1]
Workpackage title Lead
contractor
N o [2]
Person-
months [3]

Start
month [4]

End
month
[5]

Deliv-
erable
N o [6]
1 Research coordination 4 13,1 1 12 D1.1
D1.2
D1.3
2 Industrial cooperation 1 10,5 1 12 D2.1
D2.2
D2.3
3 Information dissemination 2 11,4 3 12 D3.1
D3.2
D3.3
4 Network Evaluation 3 10 3 1 D4.1
5 Management and administration 1 11,5 1 12 D5.1
D5.2
D5.3
  TOTAL   56,5      

[1] Workpackage number: WP 1 – WP n.
[2] Number of the contractor leading the work in this workpackage.
[3] The total number of person-months allocated to each workpackage.
[4] Relative start date for the work in the specific workpackages, month 0 marking the start of the project, and all other start dates being relative to this start date.
[5] Relative end date, month 0 marking the start of the project, and all end dates being relative to this start date.
[6] Deliverable number: Number for the deliverable(s)/result(s) mentioned in the workpackage: D1 - Dn.




Deliverables list

Deliv. No[1] Deliverable title Delivery
date
Nature
[2]
Dissemination
level [3]
D1.1 Roadmap of the field 6 M/12 M R PU
D1.2 Identification of promising research topics for the EC future programme 6 M/12 M R PU
D1.3 Two EUD-Net workshop reports 4M/ 12 M R PU
D2.1 Action plan for industrial area 12 M R PU
D2.2 Industrial forum report 12 M R PU
D3.1 Survey of member research projects, tools, and PhD studies 12 M R PU
D3.2 Proceedings workshop organised in conjunction with a main conference 12 M R PU
D3.3 Network web site 1 M O PU
D4.1 Evaluation report; including annotated recommendations for improvements in the consecutive months 6 M R PU
D5.1 Progress and administrative reports 6 M / 12M R PU
D5.2 Minutes of the executive committee meetings 1-12 M R PU

[1] Deliverable numbers in order of delivery dates: D1 – Dn
[2] Please indicate the nature of the deliverable using one of the following codes:
 R = Report
 P = Prototype
 D = Demonstrator
 O = Other
[3] Please indicate the dissemination level using one of the following codes:
 PU = Public.
 PP = Restricted to other programme participants (including the Commission Services).
 RE = Restricted to a group specified by the consortium (including the Commission Services).
 CO = Confidential, only for members of the consortium (including the Commission Services).

 

Last Update: July 9th, 2003